PLN Tuntaskan 14 Proyek Kelistrikan Strategis Senilai Rp12,43 T di Jawa Barat

Rabu, 30 Juni 2021 - 14:17 WIB
2. GI 150 kV Tangerang Baru II;

3. GIS Kandang Sapi Ext (Arah Plumpang)

4. Ext 2 Line Bay GIS 150 kV Antasari

5. GI 150 kV Multi Nabati Asahan (MNA)

B. Transmisi

1. SKTT 150 kV Gambir Lama II - Incomer;

2. SKTT 150 kV Plumpang - Kandang Sapi;

3. SKTET 500 kV Suralaya Lama - Suralaya Baru;

4. SUTT 150 kV Lontar- Tangerang Baru II;

5. SUTT 150 kV Tangerang Baru II - Incomer (Balaraja - Suvarna);

6. SKTT CSW II/Antasari - Incomer (Duren Tiga - Kemang);

7. SUTT 150 kV MNA Incomer Arah Serang Sirkit 2.

C. Pembangkit

1. Boiler First Firing PLTU Lontar Extension Unit #4;

2. Commercial Operation Date (COD) Steam Turbine #3 PLTGU Muara Karang Peaker CCPP (400 - 500) MW.